Arunachal Pradesh to get a Greenfield Airport in Hollongi

FacebookTwitterWhatsAppCopy Link

New Delhi: Considering the importance of air connectivity to the capital city of Arunachal Pradesh, AAI has undertaken the work of constructing a Greenfield Airport in Hollongi, 15 Kms from Itanagar. With an estimated cost of Rs.645 crore, the project includes the development work i.e. construction of airport pavements, air side work, terminal Building and city side works.

The proposed airport is designed for operations of A-320 category of air craft and future extension of Runway by 500m length to cater A-321 type of aircraft .With an area of 4100 sqm, the terminal building of the airport will be able to handle 200 passengers during peak hours. Equipped with eight check-in counters, the terminal building will have all modern passenger facilities.

Development Work is in full swing and almost 80% of airside works is completed. Progress of Construction of New Interim Terminal building is 30%. The airport is planned for operationalization on 15thAugust 2022.

The terminal will be an energy efficient building provisioned with Rain Water Harvesting system and sustainable landscape. The development work also includes construction of ATC Tower cum Technical Block, Fire station, Medical Centre and other ancillary works.